The Project

Delivering a Modern Commercial Pool for Holiday Park Guests

Crystal Leisure Swimming Pools was appointed to design, manufacture, install and commission a 20m x 10m commercial swimming pool at Unity Beach Holiday Park, creating a modern and inviting leisure facility for guests to enjoy for years to come.

The brief was to deliver a high-quality commercial pool that catered for families of all ages. The finished design incorporated a 0.5m-deep children’s splash area alongside a 1.2m-deep main swimming pool, providing a safe and enjoyable environment for both younger children and confident swimmers.

Mobile crane and groundworks on site at Unity Beach Holiday Park
01

Planning & Site Preparation

Every successful commercial swimming pool project begins with thorough planning and preparation.

Following a detailed site survey, our team carefully assessed the location, access requirements and underground services before work commenced. Extensive groundworks were then carried out, including the excavation of the swimming pool footprint and the installation of pipe trenches leading to the dedicated commercial plant room.

Precision at this stage is essential, as it provides the foundation for the entire project and ensures the pool structure, pipework and mechanical systems perform efficiently for many years.

Aerial view of the reinforced concrete pool base with the first pool section in place
02

Constructing the Pool Base

Once excavation was complete, the base was prepared using reinforcement mesh before being concreted to create a strong, perfectly level foundation capable of supporting the commercial pool structure.

Accuracy during this phase is critical, ensuring the prefabricated pool sections align precisely during installation.

Crane lifting prefabricated pool sections into position on the prepared base
03

Manufacturing & Installation

Unlike traditional in-situ concrete pools, this commercial swimming pool was manufactured off-site in a controlled warehouse environment, allowing exceptional quality control and reducing installation time on site.

The completed pool shell was transported to Unity Beach Holiday Park in six individual sections. Using specialist lifting equipment and a mobile crane, each section was carefully positioned onto the prepared base before being accurately aligned and joined together.

Following installation, our team completed the structural connections before professionally joining, sealing, tiling and grouting each section to create a seamless, watertight finish.

04

Commercial Plant Room Installation

A commercial swimming pool is only as effective as the systems operating behind the scenes.

The pool was connected to a purpose-built commercial plant room housing high-performance equipment designed to ensure outstanding water quality, energy efficiency and ease of maintenance. The installation included:

Two Commercial Heat Pumps

For efficient water heating.

Commercial Filtration

A state-of-the-art system to maintain crystal-clear water.

Automatic Chemical Dosing

Continuously monitors and maintains safe water chemistry.

Commercial Pipework

Connecting the pool to the plant room.

Before commissioning, every pipe was thoroughly pressure tested to verify the integrity of the entire hydraulic system and ensure complete reliability.

The tiled pool shell with children's splash area ahead of filling and commissioning
05

Commissioning the Pool

Following successful testing, the pool was gradually filled before our engineers carried out the full commissioning process.

This included checking water circulation, balancing water chemistry, calibrating the automatic dosing equipment, testing the filtration and heating systems, and ensuring every component operated exactly as designed.

Only once every system had been rigorously tested and met our high standards was the swimming pool handed over, fully operational and ready for guests to enjoy.

The Result

The Finished Result

The completed project provides Unity Beach Holiday Park in Devon, England, with a contemporary commercial swimming pool that combines functionality, efficiency and long-term durability.

Designed to withstand the demands of a busy holiday park environment, the facility offers guests a safe, welcoming space to swim, relax and create lasting family memories.

At Crystal Leisure Swimming Pools, we pride ourselves on delivering complete commercial swimming pool solutions, from initial planning and manufacture through to installation, commissioning and ongoing maintenance. Every project is built with quality, reliability and longevity at its core.

Your Next Project

Looking for a Commercial Swimming Pool Contractor?

Whether you’re developing a holiday park, hotel, leisure centre, school, health club or commercial wellness facility, Crystal Leisure Swimming Pools has the expertise to deliver bespoke swimming pool solutions tailored to your requirements.

Our experienced team manages every stage of the project, from concept and design through to manufacture, installation, commissioning and aftercare. Whether it’s a new build, a refurbishment, or simply a service & maintenance contract, we can help you.